North Main Canal of Chianan Canal: Baihe Irrigation Area Pumping Station

Basic information

Introduction
Due to severe sedimentation in Baihe Reservoir, its water storage capacity for irrigation had become critically insufficient. To fully address irrigation needs, the Ministry of Agriculture allocated NT$120 million to subsidize the Chianan Irrigation Management Office for the "Baihe Irrigation Area Alternative Water Source (Pipeline) Project." The project spans approximately 4.6 kilometers and involves the installation of a pressurized pumping station on the northern main line of the Chianan Canal. This station will convey water through a pressurized pipeline to the Baishui River Main Line, providing irrigation water for 602.5 hectares of farmland, effectively resolving the water needs for agricultural irrigation.