Canal North Main canal - Baihe Irrigation Area Subsidized Water Pump Station

Basic information

Introduction
Baihe Reservoir is seriously insufficient in water storage and irrigation capacity due to serious siltation. In order to completely meet irrigation needs, the Ministry of Agriculture designated NT$120 million and subsidized the Chianan Management Office’s construction of "Baihe Irrigation Area Alternative Water Source (Pipeline) construction," with a total length of about 4.6 kilometers. A pressurized pump station was built on the north main canal of Chianan Canal and the water is delivered to the Baishui River main canal by a pressurized pipeline, which is used to irrigate 602.5 hectares of farmland and provide the irrigation needed for crop cultivation.

Traffic

Area Information